Supervision of All Mechanical Works of Main Barrage and Head Regulator as following
Key Responsibilities
Preparing Monthly Schedules of works to be carried out at site.
Coordinating with Consultant and Client regarding approval of materials.
Proper issuance, Checking of direct/indirect/consumables material to their respective item codes and cost center (Materials include Electrodes, Disks Cutting Grinding, Equipments)
Coordination with subcontractors in Mechanical works
Management of Equipment and Machinery.
Making and Checking Of (B.O.Q) (B.O.M) as per drawing for supply of Equipments Materials
Radial Gates, Commissioning and Paint Along their Allied components.
Gantry Crane installation of (25 Ton 35 Ton)
Project Documentations
Knowledge about API Standards, ASME Standards AWS Standards.
Report Preparation
Quality Control.
Works as Procedures and Specification.
Inventory Records (Manual Computerized)
Maintain RITs and Field Testing Commissioning Documents.
Construction Site Management
Ensure Safety Practice during site work.
Manpower arrangements for assigned work.
Tools and Equipment arrangement and maintain it.
Raw Material arrangement as per requirement of drawing and Project Technical specification Arrangements for site Inspection, Testing and commissioning.
ASSOCIATE WORKS (OUTSIDE BARRAGE)
Pump Station at NEW KHANKI BARRAGE Monitors and analyses progress at Site.
MEP works EPC (Design and Drawings issues, Method Statements of Pumps Station,
Procurement, Delivery Storage on Site, Mechanical Works (Pumps Motors, Pipes and EOT (Electric Overhead Traveling Crane), Slide Gates Trash racks) and Electrical works.
Mechanical workshop EPC
Pre-commissioning and Final Commissioning of Centrifugal Pump.
Alignment and Overhauling of Pump Before installation.
Piping Fit-up, Flange Coupling and Welding after NDT, Radiographic Tests.
TECHNICAL SKILLS
Can read different types of drawings that include
Plot Plan
Piping Isometrics
Pipe Supports Drawings
Equipment General Drawings
General Drawings of Barrages
WPS (Welding Procedure Specification)
QIP, ITP (Quality Inspection Plans, Inspection Testing Plans)
Good command at Codes Standards.
ASME IX Boiler Pressure Vessel Code
ASME V Non Destructive Testing
ASME B 31.3 Process Piping Code
API 1104 Welding of Pipelines Related Facilities.
AWS D1.1 Structural Welding Code
INTERNSHIPS
Internship 2 weeks at Tenaga Nasional Berhad (TNB) Liberty POWER PLANT
Power Generation System
Gas Turbine (Brayton cycle)
Steam Turbine (Rankine cycle)
HRSG
Reverse Osmosis plant
Water Treatment Plant
Gas Treatment Plant (GTP)
Internship 10 days at FFC III Mirpur Mathelo Ghotki.
Urea plant
Ammonia plant
Fabrication shop
Maintenance shop
Boiler
Cooling tower