I am a self-motivated individual who thrives on succeeding in challenging situations. I am passionate about Professional development opportunities and welcome every opportunity to take my capabilities to a higher level. I welcome the opportunity to meet with you in person and discuss further the contribution I can make at organization.
 

项目

Multi Chemical Batch Project Halliburton, Jubail, Saudi Arabia
Sulphur Recovery Unit Rabigh, Saudi Arabia
Clean Fuel Unit Rabigh, Saudi Arabia
FWKO Project Rumaila Oil Field, Basra, Iraq
Solar Power Plant

工作经历

公司标识
Electrical Engineer
Al Yusr Industrial Contracting Co. (AYTB)
Dec 2018 - Oct 2021 | Rabigh, Saudi Arabia

·        Supervision of construction quality control functions/activities related to electrical disciplines.
·        Ensure compliance with the requirements of the contract scope of work, technical specification, and contract quality plan as it applies to electrical work.

Performing detailed calculations to establish manufacturing, construction, or installation standards and specifications.
Perform system expansion and improvement projects, system protection and coordination, reactive compensation, voltage analyses, distributed generation and renewable interconnections, power quality studies, and system contingency scenarios.
Apply analysis to identify the best solution to a technical problem and effectively communicate and commit to a course of action that is consistent with all legal, regulatory, code, standard, or other requirements as well as corporate policies and procedures.
Develop the next-generation distribution automation designs in close coordination with our clients.
Maintaining, implementing, or improving electrical instruments, facilities, components, equipment products, or systems for industrial purposes.
Performing a wide range of engineering tasks by operating computer-assisted design or engineering software.
Conferring with customers, engineers, and others to discuss existing or potential engineering projects.
Reviews and revises project documents for electrical and mechanical.
Interpret data, compile reports, and deliver presentations when required.
Developed strategies to determine material and labor costs, monitor crew performance, ensure health and safety regulations are obeyed, and that communications channels are open.
Helping engineering teams deliver projects on schedule.
Understanding project specifications and developing time schedules and budgets that meet them.
Observing existing processes, analyzing staff performance, and addressing deficiencies accordingly.
Monitoring and tracking project progress, and writing up reports.
Attending and scheduling meetings as required.
Delegating tasks and ensuring workers receive feedback.
Understanding and meeting all contract requirements.
Communicating with managers, supervisors, and the rest of the team.

·        MCC, EMCC, switchgear, and PDP panel installation & internal wiring in sub. station building.
·        Earthing system installation for all types of equipment.
·        Transformers and emergency diesel engine generators installation & connection.
·        Transformer busduct installation.
·        Complete ups system installation.
·        Electric motors and MOV installation.
·        Witnessed motor solo run test.
·        Ladder and perforated cable tray installation.
·        HV, LV and instrument cable testing, laying and termination.
·        Underground Electrical cables installation & connection.
·        Responsible for High Pot test, continuity testing and cold loop testing of all homerun/branch cables on site.  
·        Normal and emergency lighting system installation for the overall plant.
·        Ensure that Project relevance material and equipment are correctly received in the store, preserved and handled, identified and traceable.
·        Supervise and witness inspections, check the reports and documentation issued by inspectors and collect the required quality records.
·        Plans/Inspection Test Plans, obtain and collect the relevant documentation also for the purpose of approvals of mechanical completion of the plant system.
·        Make site construction personnel aware of and trained them (Like a Quality Control Tool Box Talk) on Quality topics relevant to Electrical Works.
·        Ensuring the Inspection is carried out as per ITP.

Analyzing technical drawings and providing material and cost estimates.
Ensuring all projects are completed on time and within budget.
Experience in planning, design and implementation of electrical engineering projects in an international environment.
Experience in engineering logistics in support of field operations.
Experience in research and development of sourcing solutions related to electrical and mechanical.
Experience in the use of data analysis systems and visualization tools.

公司标识
E&I ENGINEER
AL-KARRAR ENGINEERING COMPANY (RUMAILA OIL FIELD)
May 2017 - Sep 2018 | Al Basrah, Iraq

·        Prepare various strategies for all planning activities for projects.
·        Maintain all asset investment plans and ensure compliance with capital expenditure.
·        Ensure accuracy for all operational requirements for projects and achieve all investment objectives.
·        Evaluate all system capacity and analyze all production requirements and system deficiencies.
·        Provide support to all operations and extension requests.
·        Manage work as per component technical resource for all Water System Plans and assist to prepare all capital plans and project requirements.
·        Analyze all engineering activities for all internal and external departments.
·        Prepare required presentations for all regulatory agencies.
·        Develop required to enhance the performance of planning projects.
·        Manage all communication and provide efficient feedback for all processes.
·        Ensure optimal utilization of all common tools and processes.
·        Prepare plans and schedules for all project delivery.
·        Recommend appropriate improvements and ensure optimal quality of all project schedules and evaluate reports.
·        Perform regular analysis of all schedule trends.

Installation of electrical equipment, instrumentation, controls, components and systems.

·        Review of all relevant documents including but not limited to loop drawings, logic diagrams, cause and effect sheets, JB drawings, termination drawings, Instrument hook-up drawings and cable schedules.
·        Responsible for all the arrangements and installation of instruments like control valve, transmitters, thermocouples, SOV’s etc.
·        Responsible for the installation of all field instrument like motor operated valve, manual by-pass valves, emergency block valves,  temperature transmitters, flow meters, pressure transmitters, pressure gauges, , pressure relief valves, pressure indicators, control valve, transmitters, thermocouples, SOV’s etc.
·        Installation of control valves, pneumatic fittings, pneumatic tubing’s, nut & bolts, gaskets, and all other instruments material installed.
·        Installation of instrument control panel with proper quality check.
·        DCS and SIS panel installation & wiring in control room.
·        Control room management consoles system installation.
·        IT panel installation & wiring in telecommunication room.
·        Variable speed drive installation(VFD’s), connection and pre-commissioning.
·        Ensure compliance with the requirements of the contract scope of work, technical specification and contract quality plan as it applies to E&I work.

Inspecting E&I equipments for control and instrumentation systems to ensure compliance for plant, pipeline and other system performance.

·        Responsible for  Testing, Installation and Fire and Gas detection system for the Substation and Control room.
·        Responsible for FO cable testing and splicing work.
·        Monitoring of overall project schedule and ensuring the important project milestone & deadlines are met.
·        Reviewing engineering drawings and documents and ensuring same comply with project specifications.
·        Supervise and witness inspections, check the reports and documentation issued by inspectors.

Estimate the required Manpower, materials, tools and equipment requirements for any electrical scope of work.
Assisting permit receiver HSE permit to work.

·        Make site construction personnel aware of and trained them (like a quality control tool box talk) on quality topics relevant to electrical and instrumentation works.
·        Inspection, testing, installation and configuration of Instruments and relevant control systems.

Preparing the BOM (Bill of Material) and BOQs (Bill of quantities) for the Electrical scope of work in compliance with Project Engineering Specifications.

·        Assisting the procurement/material coordinator in the task of overseeing final checking.
·        Ensuring compliance with health and safety legislation.

公司标识
Electrical Engineer
TBEA Xinjiang Sunoasis Co., Ltd. (TBEA Sunoasis Co., Ltd.)
Nov 2015 - Feb 2017 | Bahawalpur, Pakistan

• Planning and execution of the Preventive Maintenance program and improve the reliability of the Electrical equipment.
• Regular Monitoring of HMI and SCADA system.
• Laying, Termination and testing of HV &LV cables.
• Maintenance of Power transformer, C.B. (SF6 & Vacuum) CTs, PTs, insulators, isolators etc.
• Troubleshooting according to faults.
• Protection system of transformer.
• Noted readings in control room.
• Creating maintenance procedures.
• Fitting new parts and making sure equipment is working correctly.
• Working in collaboration with the production team to formulate the best cost-effective manufacturing process.
• Fix and maintain lighting fixtures and fittings.
• Learn new skills and attend training programs in other to increase knowledge of trends and best practices in the industry.

公司标识
Internee Engineer
GENCO’S HOLDING COMPANY LIMITEDNorthern Power Generation Company limited, Thermal PowerStation
Jun 2014 - Aug 2014 | Muzaffargarh, Pakistan

• Working of Electric Generators and Motors.
• Knowledge about the protection & maintenance of Electric Generators & Motors.
• Monitoring of all electrical work and collect the report in soft and hard form.
• Study of Control Panels and Switch gear Panels.

学历

Islamia University
学士, 技术学士, Bsc. Electrical (Power) Engineering‎
Energy and Power
CGPA 3.1/4
2015

技能

熟练 Accounts Management Sklis
熟练 Analytical Skills
中级 Autodesk Navisworks
初学者 Automotive Electronics Knowledge
熟练 Cloud, Server
熟练 Construction Drawings
中级 Cost Estimates
初学者 Developing Budgets
中级 Distribution Designs
中级 Electric Power Management
中级 Electrical Code
中级 Electrical Controls
熟练 Electrical Engineering
初学者 Electrical Estimating
中级 Electrical Repair
初学者 Electronics Repair
熟练 Energetic Skills
中级 Energy Generation
中级 Equipment Maintenance
中级 Facilities Management Systems
中级 Fire Alarm Devices
熟练 Marketing Implementation
初学者 MATLAB Command
中级 Microsoft Excel
熟练 Multitasking Skills
初学者 Oracle Primavera P6
初学者 PLC Programming (Ladder logic)
初学者 Power Electronics Designing
熟练 Presentations
中级 Product Documentation
中级 Safety Management
中级 Safety Standards
初学者 SIMATIC MANEGER (SIEMENS PLC)
中级 Staffing
熟练 Technical Understanding
熟练 Understanding Of Diagrams

语言

熟练 乌尔都语
初学者 阿拉伯语
熟练 英语

关注的公司