Having 6 Years of professional experience in Project Planning, Project
Execution & Control, Commissioning and Testing.
Well conversant with Engineering codes and standards.
Remarkable experience in resource management.
Safety process oriented along with proven technical and training skills.
Supported the short terms & Long term projects consisted of the turnkey Solutions.
NETRACON Technologies concentrates on the international and domestic Electric Power &
Telecom market as its major goal. Constructing, operating & upgrading Transmission Lines, Grid
Stations & Telecom Sites are the major undertakings, NETRACON has all the technical know-how
and expertise to manage such projects irrespective of the site conditions, situations or the voltage
levels.
Projects:
ADB-103: Procurement of Plant – Design, Manufacturing, Supply, Installation, Testing &
Commissioning of Protection Relays, Fault Recorders, Fault Locators and Event Recorders
of NTDC system in South area.
Design, Manufacturing, Supply, Installation, Testing and Commissioning of Plant for
500/220/132 KV Faisalabad (West) Substation
The company was established in 2012 years, investment by SEMC Group the
famous brand is SEMC, all electric motor, metallurgy machinery payment and import
and export by Chinese State-owned enterprise. Specialty in manufacturing of AC & DC
motorsDesign, manufacture and installation of metallurgical equipment and AC and DC
motors and relation steel mill equipment.
Designated as, “International Sales Engineer”
Installation, Supervision, Pre-Commissioning, Commissioning & Start-Up Services At
OGDCL MELA Development Project At SHAKARDARA District KOHAT,KPK
Branch Main office in DHA Lahore, well known Chinese company having complete
manpower solution and internationally involved in EPC projects.
Construction of Line-III 7700TPD Cement Plant at Power Cement Ltd NOORIABAD.
Major responsibilities:
Electrical & Instrument erection for overall new cement plant construction.
Project 1: Erection, Commissioning & Testing of New Tile Bond Plant at Bestway Cement Limited, Farooqia (BCL), District Haripur, KPK
Project 2: Erection, Commissioning & Testing of Clinker Shed Pan Conveyor Extension at Bestway Cement Limited (BCL), Farooqia, District Haripur, KPK
Project 3: Erection, Commissioning & Testing of New Cement Mill at Bestway Cement Limited (BCL), Farooqia, District Haripur, KPK
Project 4: Installation of HT Lines at Bestway Cement Limited (BCL), Farooqia, District Haripur KPK
Project 5: Cooler Extension with Complete Earthing mesh at Bestway Cement Limited (BCL), Hattar, District Haripur KPK
Project 6: Erection, Commissioning of Line-2 at Fauji Cement Company Limited (FCCL), Village Jhang Bahtar, District Attock Ongoing.
Job Responsibilities:
To review electrical drawings & technical specifications, conduct necessary calculations and develop charts and graphs.
Erection of HT & LT transmission line & sub-station (33KV).
To co-ordinate with the third party for Electrification, Execution, Erection & Commissioning.
Attending site meetings.
To provide the entire electrical solutions as per requirement.
To develop work break down structure (WBS) of a project for better
scheduling and control.
To monitor and control all execution activities by ensuring their quality.
Project: Electrical & Instrument Erection & Commissioning for Waste Heat Recovery Power Project (WHRPP 6MW) -Bestway Cement Company Ltd at Farooqia, District Haripur KPK, Pakistan.
Job Responsibilities:
Complete Erection & commissioning of Electrical & Instrument works.
To review electrical drawings & technical specifications to conduct necessary calculations & develop charts & graphs.
Attend site meetings.
Generate ITRs/RFIs.
Generate Invoices & their verification from client.
Mobilize manpower for different work fronts.
Attend HSE Training.
Material handling & execution.
To discuss with client for more work fronts.
Project: BOP Up-rate & Up-gradation of control system from MARK IIe to MARK VIe Control System at 600MW (GE based Power Plant) Thermal Power Station GUDDU,Sindh,Pakistan.
Worked as "Trainee Electrical Engineer". Supported Electrical & Control Jobs.
Job Responsibilities:
Generate Daily Progress Reports & RFIs.
Verification of RFIs by Client.
Review AutoCAD drawings of E&I to meet the requirements.
Attended training of MARK VIe Control System (MARK VIe) & Distributed Control System (DCS).
Resource allocation.
To coordinate with third party for electrification & execution.
Attend site meetings.
To monitor & control all execution activities by ensuring their quality.