Having experience of More than 10 years on a large scale projects in Saudi Arabia,Dubai,Abu Dhabi and Pakistan in
Power and energy,Buildings, Housing community and Power plants.Working on Primavera P-6.
5 Years experience in planning in Pakistan
5 Years experience in Planning and cost control in UAE & KSA
Working with Habib Rafiq (Pvt.Ltd) –Lahore reporting to Senior General Manager, Mr. Mohsin Aziz has the following expertise/capabilities:
Prepare Progress S Curves, manpower histograms and cash flows.
Record the planned and actual progress on weekly basis and discuss the variance to bring the project planned progress.
Attend Progress control meetings with client, Project Management Consultancy and other stakeholders on Weekly basis.
Analyze the subcontractors programs, weekly and monthly reports and provide them recommendations.
Prepare weekly and monthly target programmes for the site team and offsite team and regulate them.
Production of monthly progress reports monitoring progress against the agreed project program and the financial status of the respective sub-contracts. .
Assist the assigned Senior General Manager in tracking the project against its schedule, budget and against phase review objectives.
Working with Arabian BEMCO –Qaseem Saudi Arabia reporting to Project Director, Mr. Mohsin Aziz has the following expertise/capabilities:
Prepare Baseline Programs using Planning software Primavera P6.0 in line with project management and planning tool and techniques.
Preparation of IPC on monthly basis and getting verified from Client.
Prepare Progress S Curves, manpower histograms and cash flows.
Record the planned and actual progress on weekly basis and discuss the variance to bring the project planned progress.
Prepare monthly and weekly progress reports.
Attend Progress control meetings with client, Project Management Consultancy and other stakeholders on regular basis.
Analyze the subcontractors programs, weekly and monthly reports and provide them recommendations.
Preparation of Manpower efficiency reports on weekly basis for main activities and highlighting deviation from budgeted man-hours.
Prepare weekly and monthly target programmes for the site team and offsite team and regulate them.
Production of monthly progress reports monitoring progress against the agreed project program and the financial status of the respective sub-contracts.
Duties & Responsibilities: Reporting to Project Director, Mohsin Aziz remained responsible for the following:
Preparation and reviews of Baseline Programs for projects under civil division scope.
Preparation of Weekly progress reports for all projects.
Preparation and update of resources histograms, progress curves, cash flows.
Attend progress control meetings with Client and PMC.
Record minutes of meeting and analysing appropriate action of the parties.
Evaluate and update the progress on weekly basis and discuss with senior management.
Review and monitor the project status through updated programs and internal meetings.
Preparation of look ahead schedules for all projects and alarming the critical activities.
Analysing Critical Path and sequencing of dependent activities to avoid project delay.
Assisting Project Director in preparing resource allocation schedule, weekly progress report and monthly progress reports.
Site visits to projects to verify the progress reported for all projects.
Duties & Responsibilities: Reporting to Project Director, Mohsin Aziz remained responsible for the following:
Prepare Baseline Programs for the Construction of the Al Ghadeer Development Package-1 Abu Dhabi Project.
Prepare the cash flows, manpower histograms, progress S Curves and cash flows of the respected job.
Keep updating the program on weekly basis and recording the planned progress vs. actual progress.
Attend and manage weekly progress meetings with Client and Project Management Consultants for the purpose to have proper progress throughout the project duration and to have smooth flow of information between stakeholders.
Prepare look ahead schedules to forecast the future activities.
Prepare monthly and weekly reports for Client.
Discuss and monitor the progress and resources with management.
Duties & Responsibilities: Reporting to Project Manager, Mohsin Aziz remained responsible for the following:
Preparation and review of Baseline Programs for Client and Consultants as per project scope.
Preparation of updated and Time impacted programs.
Preparation and update of resources histograms, progress curves, cash flows.
Evaluate and update the progress on weekly basis and discuss with senior management.
Review and monitor the project status through updated programs and internal meetings.
Preparation of look ahead schedules for team and making analysing thoroughly.
Analysing Critical Path and sequencing of dependent activities to organize in best way.
Assisting Sr. Manager in preparing resource allocation schedule, weekly progress report and monthly progress reports.
Duties & Responsibilities: Reporting to Project Manager. Mohsin Aziz remained responsible for the following:
Preparation of Baseline programs in coordination with the Project Manager;
Preparation of Resource Histograms, Cash flows and Progress S Curves.
Preparation of Weekly and Monthly progress reports for Clients and Consultants
Procurement of all required materials as per site request after ensuring the IFC quantities.
Coordination with project team in order to make sure the project is on track.
Attend progress control meetings with clients, consultants and other stakeholders.
Assistance to Project Manager in meetings with Client, Contractors, Consultants and preparation of relevant presentation, MOM, follow up and reviewed action thereof.
Review subcontractors programs, organising their resources and daily activities.
Assistance to the Project Manager in site related issues, progress meetings, preparation of responses/ clarifications, and pass on instruction to site team and Engineer’s Representative.