·       Detailed monitoring of rehabilitation works as per approved drawings and specifications.
·       Maintaining daily & weekly reporting system.
·       Meeting on daily Basis for Progress on Field, HSE, and Different Issues Regarding Quality of work.

公司标识
Site Engr.
Shefai Engineering and Construction Pvt. Limited
Jun 2019 - Feb 2020 | Jhang, Pakistan

 
Fabrication, Erection of Interconnecting Piping
·       Complete study of piping layouts, isometrics & Method statement.
·       Meeting on daily Basis for Progress on Field, HSE, and Different Issues Regarding Quality of work.
·       Supervision to Fabrication Team for Pipe as per ASME Standard and Safe Handling at site for Erection.
·       Maintain inspections, testing & commissioning documentation as per Client, QA/QC & safety procedures.

公司标识
Site Engr.
Sinohydro corporation ltd
Apr 2017 - Jun 2019 | Jhang, Pakistan

·                 Conducted Inspection of Installed gate equipment whichincludes:
-          Dimensional Checks
-          Survey / Alignment checking
-          Installation Methodology
·                 Assists Senior Engineer to Review:
-          Drawings / Design
-          Method Statements
·                 Assist Senior Engineer in:
-          Project Coordination with Client & Consultant.
-          Technical issues.
·                 Preparation of Technical Reports / Letters.
·                 Preparation of Daily / Weekly / Monthly Progress Reports.
·                 Ensure Implementation of HSE plan at site.

公司标识
junior engineer
national development consultan pvt ltd
Oct 2016 - Mar 2017 | Muzaffarabad, Pakistan

Working as Junior Engineer in Steel Lining Factory of Neelum Jhelum Hydro Electric Project (969MW).
   Inspecting different Cutting Operations like Blanking & Grooving on Highly Quenched and Tempered HSS (Tensile Strength=660 MPa & Yield Strength=550 MPa) performing by contractor(CGGC).

Reviewingthe drawings provided by the Contractor.
Inspecting Rolling Operationand Radiantesting of platesby using radian testingtemplate. Inspecting Alignment of Rolledtiles by using spider, jigs and screw jacks.
Inspecting welding (3G, SMAW, and Butt Joint) for fabrication.
Inspecting Roundness Correction by using weld angular correction machine when fabrication of 3m cane is completed.
   Inspecting installation (1G &4GWelding)of stiffen erring sand providing consultancy to the contractor.
Supervising the welder’s qualification testfor 1G, 2G, 3G & 4G welding processes. Supervising Ultrasonic test of welding performing by Contractor.
Inspecting Fillet welding (SAW)of canes. Measuring Fillet Leg using Palm grin Gauge.
Inspecting circumferential welding (MIG, SAW) for fabrication of 6m canes. Providing Consultancy in Non-Destructive Testing of welds like Radiography Test, Ultrasonic test, Dye Penetrate Test
Interpreted more Five Hundred. Spent more than12000 minute on UT.
Inspecting the Anti-Corrosion procedures like Grit Blastingwith Sa 2.5 grade grit material. Inspecting the Painting i.e. AMERCOAT78HBC on 12 m length Steel can shave diameter of 6.6m.

公司标识
sitenEngineer
Nishan Engineer Pvt Ltd
Jul 2015 - Sep 2016 | Okara, Pakistan

Supervision of Welding Works involved in fabrication and installation of gate equipment and superstructures. Major responsibilities include:
o    Visual examination of work in progress and effective supervision of repair procedures.
o    Inspection of use of filler material depending on the base material so as they comply approved welding procedures.
o    Checking and quality inspection of welded joints during technical process and control results
o    Checking and inspection of welds so as they should be performed incompliance with Approved welding procedure (WPS).
o    Coordination of welding activities for processes: SMAW, GTAW, GMAW.
o    Ensure that all Welding operations are executed in safe working environment and implementation of standard welding rules.
o    Supervision of welding procedures tests and monitor welding works at site.
o    Inspection of welds before, during and after welding.
o    Ensure implementation of Standard and Approved welding procedures.
·                 Conducted Inspection of Welding Works using following NDT Techniques:
-          Radiographic Technique
-          Ultrasonic Technique
-          Dye-Penetration Technique
·                 Supervision of fabrication works carried out by Contractor at site workshop.

公司标识
Site engineer
Sinohydro corporation ltd.
Jul 2014 - May 2015 | Pak Pattan Sharif, Pakistan

 
·                 Erection/installation of embedded part of slide Gates.
·                 Erection/installation of slide Gates of Cross-Regulators at PC upper.
·                 Preparation of Daily / Weekly / Monthly Progress Reports.

学历

University of Lahore
学士, 理工学士, BSc(Hon;s) in Mechanical Engg.‎
Mechanical Engineering
CGPA 3.0/4
2014
GOVT. COLLEGE (B) JAMPUR RAJANPUR.
中级/A级, 理学院(工程预科), ‎
Mathematics
等级 B
2010
al-kamal boys high school jampur
大学入学/0级, 科学, ‎
Biology
所占比重 75%
2008

语言

熟练 Saraiki
熟练 乌尔都语
中级 英语