Having 07+ years of experience as Quantity Surveyor Seeking a challenging Research & Development oriented career within a dynamic and progressive organization where enthusiasm, dedication and the ability to manage tasks effectively are prerequisite in driving the organization.
Responsibilities as Quantity Surveyor: Preparation of Payment Invoices and Interim Payment Certificate. Preparation of BOQ & Bar Bending Schedule. Preparation of Petty Contractors Bills. Managed consultant engineers for dispute resolution. Maintained quantities for final account and variations purposes. Estimate of all Civil Quantities for material requirement. Materials Reconciliations. Preparation of Cost Analysis. Rate Analysis. Support Site execution team by providing IFC drawings. Review and implement all supporting documents regarding project execution. Support QC team to record site changes for as-built drawings & will be submitted to client accordingly. Construction Claims, Contracts, Standard of Measuring and more as per site requirement and instructions by the In charge.
Projects Handling at the same time1) Name-Bejaan Resort Chitral KPKCost -1390 million.Works- (Structure Works, Finishing Works,Boundary wall and Parking Area) Project Status -Ongoing..Client -Amaan Pvt Ltd.Consultant - Ali Arshad Associates
2) Name-Mcdonald's Canal View Lahore Cost -70 million.Works- (Structure Works, Finishing Works,Boundary wall and External Works) Project Status- CompletedClient -Siza Foods Pvt Ltd.Consultant- Ahed Associates-70 days Project
3) Name-Mcdonald's Barkat Market Lahore Cost -77 million.Works- (Structure Works, Finishing Works,Boundary wall and External Works) Project Status- CompletedClient -Siza Foods Pvt Ltd.Consultant- Ahed Associates-70 days Project
4) Name-Master Textile Raiwind Cost -520 million.Works- (Structure Works, Finishing Works,Road Works) Project Status- Completed Client -Master Textile Pvt Ltd.Consultant- Chisty Brothers
5) Name-Mcdonald's Haro South & North Islamabad M-1 Cost -80 million.Works- (Structure Works, Finishing Works,Boundary wall and External Works) Project Status- CompletedClient -Siza Foods Pvt Ltd.Consultant- Ahed Associates-70 days Project
6) Name-Mcdonald's Askari-II Lahore Cost -80 million.Works- (Structure Works, Finishing Works,Boundary wall and External Works) Project Status- CompletedClient -Siza Foods Pvt Ltd.Consultant- Ahed Associates-70 days Project
7) Name-Mcdonald's Civil Line Faislabad Cost -100 million.Works- (Structure Works, Finishing Works,Boundary wall and External Works) Project Status- CompletedClient -Siza Foods Pvt Ltd.Consultant- Ahed Associates-75 days Project
8) Name-Mcdonald's Lake City Lahore Cost -100 million.Works- (Structure Works, Finishing Works,Boundary wall and External Works) Project Status- CompletedClient -Siza Foods Pvt Ltd.Consultant- Ahed Associates-75 days Project
9) Name-Mcdonald's Centeral Park Lahore Cost -100 million.Works- (Structure Works, Finishing Works,Boundary wall and External Works) Project Status- CompletedClient -Siza Foods Pvt Ltd.Consultant- Ahed Associates
10) Name-Imtiaz Mall E-11 Islamabad Cost -300 million.Works- (Finishing Works,Boundary wall and External Works) Project Status- ongoing Client -Imtiaz Stores
11) Name-Noor Poultry Pattuki -450 million.Works- (Structure Works,Finishing Works,Boundary wall and External Works) Project Status- ongoing Client -Sheik Noor-o-Din
12) Name-Noor Poultry Nilla Dulla Islamabad -200 million.Works- (Structure Works,Finishing Works,Boundary wall and External Works) Project Status- ongoing Client -Sheik Noor-o-Din
1) Name-Nishat Textiles Extension Ferroz Wattwan Cost -40millionsWorks- (Structure Works, Finishing Works,Road Works) Project Status- CompletedClient -Nishat Textile Pvt Ltd.Consultant- AAA Associates
2) Name-Nishat Textiles Extension Bhikhi Cost -75millionsWorks- (Structure Works, Finishing Works,Road Works) Project Status- CompletedClient -Nishat Textile Pvt Ltd.Consultant- AAA Associates
3) Name-DIN Textiles Housings Colony Cost -450millionsWorks- (Structure Works, Finishing Works,Road Works,MEP Works) Project Status- Completed Client -DIN Group Pvt Ltd.Consultant- Akbar and Associates
1)Name-DG khan Cement Factory HUB Balochistan Cost -approx 4000 millionWorks- (Structure Works, Finishing Works,Road Works) Project Status- CompletedClient -DG Cement Consultant- A.A.A Associates
1)Name-LDA Sports Complex China Scheme LHRCost -40millionsWorks- (Structure Works, Finishing Works,Road Works,MEP Works) Project Status- CompletedClient -Lahore Development Authority Consultant- NESPAK