Working in Pak Elektron Limited (PEL), I am appointing as Site Engineer of Engineering Procurement
Construction (EPC) Department in Project of Underground Electrification and Street Light system of DHA Lahore
different phases. Here, I am responsible of site execution like installation of PMTs, RMS, DBs, Poles and SLCPs also
termination kiting, earthing of electrical equipments. Supervise excavation for laying of Feeders, HT cables, LT cables and street light cables in measured trenches. Performing Megger test, Hipot test for commissioning of site is the major part of my responsibilities. After it follow the documentation protocol of Client and finalize invoices for bill claiming from Client and reported to project engineer.
Working in Nestle factory Sheikhupura, I am appointing as Electrical Engineer Field Supervisor through contractor ASEC, Here I supervise installation, maintenance checking of electrical instruments like power DBs, Cable dressing, installation of circuit breakers, Relays, magnetic contactor in control panel then reporting to project manager of Nestle Factory.
Working in Excel surveyors, Lahore, Punjab, Pakistan. As Surveyor Engineer I am going to Power Plants, Industries , Factories for inspection of their power house when any device like Generator from 575 KW to 6.5 MW, Transformer 220KVA to 25000KVA etc got damage. In my survey I carry out the cause of damage then report to my company and making the engineering damage report in subject loss.
Working in the Zong Cmpak , Lahore, Punjab, Pakistan. In Telecommunication tower I worked to control the power of whole site and distribution of power for entire site’s equipment. I am able to maintain performance of all telecom equipment at a site. I was responsible for Controlling SDR at Telecom tower site also responsible for reducing outage of site between load shedding.
Working in the NTDC Wadpa Town 220kV Grid Station I learnt the transmission mechanism and the distribution
of the energy to other Grids. The tapping procedure of transformers, shifting and dividing the load to the two
buses, loadshedding procedures, maintenance of the system, insulation of the transmission wires, CTs & PTs
working, the role of isolators & breakers in the protection of the system, importance of SF6 and wave traps.