Electrical Engineer with (10) ten years’ of practical working experience in Construction and Management of Dam & Hydro Power Projects throughout the lifecycle. My area of expertise includes:
· Project Management · Project Planning · Contract Implementation · Cost Estimation · Review of Feasibility · Bidding documents / technical specifications · Engineering Designs Reviews · Technical Reporting · Claims and Variation Orders · Construction Management & Supervision · Quality Assurance/Quality Control · M&E and Civil Interface · Electrical & Mechanical Equipment’s, Assembling, Installation, Testing and Commissioning · Transmission Line (LT & HT) 11kV, 66kV and 132 kV · Grid Station · Switchyard (AIS & GIS) · Control and Protection System · SCADA and Automation System · Telecommunication · Instrumentation · Health & Safety
Active engagement in project management activities through verbal/written correspondence and project coordination with project stakeholders. Firm knowledge and utilization of applicable international standards and WAPDA/NTDC Standards/Guidelines for the projects.
· Coordination and attend meetings with Provincial Government of Gilgit Baltistan and other government/private departments regarding electricity management and drinking water.
· Operation and Maintenance of Dam and 04 No.s Hydro power Plants of capacity 17.66 MW (both Electrical and Mechanical equipment’s)
· Procurement and store management.
· To look after financial matter of the office.
· Office and staff management.
· Preparation and to update the dam data on daily basis.
· Attend the high officials during visit to Satpara Dam.
· To ensure safety during maintence work.
1- Review the feasibility report, tender documents, bidding documents, contractor’s designs and documents, making recommendations for changes or adjustments to the designs, drawings or specifications where necessary.
2- Review and Implementation of Project Quality Plan.
3- Review the detailed requirements and standards to be used during construction to be submitted by the contractor with their installation and the specifications of the equipment with regard to international and local standards.
4- Review of work procedures / method statements proposed by contractors and suggesting improvements in accordance with project specifications and contract requirements.
5- Review of technical data, designs, construction drawings, shop drawings, as-built drawings etc. submitted by contractor.
6- Supervise the assembling installation, Testing and Commissioning of Generator, turbine, Governor, transformer, LV/MV Switchgears, Transmission lines(11 kV, 132 kV), switchyard (AIS & GIS), Grid station, Control Protection, SCADA & Automation System, Penstock (welding & testing), Crane(Gantry Crane, bridge Crane), gates etc.
7- Processing and evaluation of claims submitted by the contractor.
8- Checking of BOQ according to specification of equipment and contract document.
9- Checking and verifying physical measurements and evaluation of the works done and certifying relevant payments against works done by the contractor as per contractual procedures (Issuing Interim Payment Certificates / IPCs).
10- Assisting in preparation of Variation orders (VO’s), Extension of Time (EOT’s) and Monthly Statements (MS) as per Contract Provisions.
11- Assisting in processing and issuance of variation orders and substantial completion certificates after obtaining consent of the client and assisting in issuance of all certificates to the client for correct payment to the contractor.
12- Evaluation of EOT submitted by the contractor.
13- Implementation of Approved Construction Schedule and preparation of Recovery plans to overcome the delays.
14- Co-ordinate with the Team Leader and Senior Engineers for procedures and scheduling for the installation of all equipment.
15- Witness of FAT and site tests of equipment’s and review the reports submitted by the contractors during manufacturing of the equipment’s and when require by the employer.
16- Assist the contractors to develop and co-ordinate detailed test procedures for both dry and wet commissioning and participate in of these tests.
17- Review the relevant sections of the operation and maintenance manuals and check that the spare part lists and documentation is complete.
18- Advice the Site Engineer and supervise installation work at key times during construction.
19- To determine the requirements for the Civil and Mechanical works on site to ensure compatibility and co-ordination.
20- Monitoring and managing of site progress as per approved work plan to achieve the target in time.
21- Assist the HSE team for implementation of Safe working hours during construction, and also during installation, testing and commissioning.
22- Pre-commissioning and Commissioning of hydropower plant.
23- Multiple Units commissioning of hydropower plant.
24- Powerhouse Complex Commercial Operation Tests of hydropower plant.
25- Preparation of Project Completion Report, Minutes of Meetings and Site visit reports, Annual, Quarterly and Monthly progress reports.
1- CONST. of 0.7 MW Hydropower project at Hassan Abad.
2- Post Flood Reconstruction of Hydel Power Station at Bordas Balghar.
1- To conduct technical and managerial meetings with the subcontractors and Government Departments.
2- Implementation of Approved Construction Schedule and preparation of Recovery plans to overcome the delays.
3- Preparation of Annual, Quarterly and Monthly progress reports.
4- Preparation of Minutes of Meetings and Site visit reports
5- To deal the Non-Conformance reports, Site Memos and technical letters as per contract Clauses.
6- To manage Electrical & Mechanical site activities (assembling, installation, testing and commissioning) of weir control room, gates etc., powerhouse (Generator, Transformer, Governor, Turbine, runner, Switchgear(MV/LV) room, Control Panels, SCADA System, Control and protection system, Flood / water measuring system, Transmission line, GIS, AIS, Cable trays, Internal / External electrification work, Penstock (Fabrication, Welding and testing) etc.
7- Review and Implementation of Project Quality Plan
8- Review of technical data, designs, construction drawings, shop drawings, as-built drawings etc.
9- To check site design adequacy of Electrical and Mechanical works in coordination of civil team.
10- Coordination with design groups, where required, for design requirements at site and proposed changes in design as per site requirement.
11- Monitoring and managing of site progress as per approved work plan to achieve the target in time.
12- Assist the HSE team for implementation of Safe working hours during construction, installation, testing and commissioning.
1- Review the feasibility report, tender documents, bidding documents, contractor’s designs and documents, making recommendations for changes or adjustments to the designs, drawings or specifications where necessary.
2- Review and Implementation of project execution and Quality Plan.
3- Review the detailed requirements and standards to be used during construction to be submitted by the contractor with their installation and the specifications of the equipment with regard to international and local standards.
4- Review of work procedures / method statements proposed by contractors and suggesting improvements in accordance with project specifications and contract requirements.
5- Review of technical data, designs, construction drawings, shop drawings, as-built drawings, Testing and Commissioning report, etc. submitted by contractor.
6- Supervise the assembling installation, Testing and Commissioning of Generator, turbine, Governor, transformer, LV/MV Switchgears, Transmission lines(11 kV, 132 kV), switchyard (AIS & GIS), Grid station, Control Protection, SCADA & Automation System, Penstock (welding & testing), Crane(Gantry Crane, bridge Crane), gates etc.
7- Processing and evaluation of claims submitted by the contractor.
8- Checking of BOQ according to specification of equipment and contract document.
9- Checking and verifying physical measurements and evaluation of the works done and certifying relevant payments against works done by the contractor as per contractual procedures (Issuing Interim Payment Certificates / IPCs).
10- Assisting in preparation of Variation orders (VO’s), Extension of Time (EOT’s) and Monthly Statements (MS) as per Contract Provisions.
11- Assisting in processing and issuance of variation orders and substantial completion certificates after obtaining consent of the client and assisting in issuance of all certificates to the client for correct payment to the contractor.
12- Evaluation of EOT submitted by the contractor.
13- Implementation of Approved Construction Schedule and preparation of Recovery plans to overcome the delays.
14- Co-ordinate with the Team Leader and Senior Engineers for procedures and scheduling for the installation of all equipment.
15- Witness of FAT and site tests of equipment’s and review the reports submitted by the contractors during manufacturing of the equipment’s and when require by the employer.
16- Assist the contractors to develop and co-ordinate detailed test procedures for both dry and wet commissioning and participate in of these tests.
17- Review the relevant sections of the operation and maintenance manuals and check that the spare part lists and documentation is complete.
18- Advice the Site Engineer and supervise installation work at key times during construction.
19- To determine the requirements for the Civil and Mechanical works on site to ensure compatibility and co-ordination.
20- Monitoring and managing of site progress as per approved work plan to achieve the target in time.
21- Assist the HSE team for implementation of Safe working hours during construction, and also during installation, testing and commissioning.
22- Pre-commissioning and Commissioning of hydropower plant.
23- Multiple Units commissioning of hydropower plant.
24- Powerhouse Complex Commercial Operation Tests of hydropower plant.
25- Preparation of Project Completion Report, Minutes of Meetings and Site visit reports, Annual, Quarterly and Monthly progress reports.
1-To present site progress related to E&M works regarding technical issues during Lenders, Owners and insurer visits.
2- To conduct technical and managerial meetings with the concerned departments of contractors, sub-contractors.
3-Assist the HSE team for implementation of Safe working hours during construction, installation, testing and commissioning.
4- Verification physical measurements and evaluation of the works done and processing of Interim Payment certificates (IPC) in accordance with approved milestone as per EPCC/FIDIC contract.
5- Assisting in processing and issuance of variation orders,Extension of Time (EOT’s) and substantial completion certificates after obtaining consent of the client and assisting in issuance of all certificates to the client for correct payment to the contractor.
6- Preparation of Annual, Quarterly and Monthly progress reports.
7- Preparation of Minutes of Meetings and Site visit reports
8- Issuance of Non-Conformance reports, Site Memos and technical letters as per contract Clauses.
9- To manage and supervise E&M site activities i.e assembling, installation, testing and commissioning.
10- Review of work procedures / method statements proposed by contractors and suggesting improvements in accordance with project specifications and contract requirements.
11- To check site design adequacy of Electrical and Mechanical works in coordination of Civil team.
12-Assisted in the evaluation of pre-qualification documents (electrical part) submitted by the different contractors.
13- Pre-commissioning and Commissioning of hydropower plant.
14- Multiple Units commissioning of hydropower plant.
15- Powerhouse Complex Commercial Operation Tests of hydropower plant.