Have 2-years of experience in a leading textile and FMCG companies in Pakistan as Automation Engineer, where I designed HMI, SCADA, and PLC ladder logic configuration and 1-year experience in a construction company in Saudi Arabia as Electronics Engineer, where I worked in a Project Under SEC(Saudi Electric Company) for the construction of a 110kv/33kv/13.8kv substation in Taif region, where I:
Handled the work related to Electrical&Electronics at the construction of a substation in Taif, Saudi Arabia from installation to the energization of the project, which include:
Testing of the 33kv and 13.8kv AIS and 110kv GIS.
Scheme check of protection panels.
AC, DC lighting and supply panels scheme and commissioning.
Installation and testing of PLC.
SAS system and HMI troubleshooting.
Rectification of faults.
Supervision of Fiber Optic installation and testing.
Protection relays configuration and scheme check.
Scheme check of all type of auxiliary relays.
Worked with the qualified electronics engineers and learned about the working of industrial PLCs and their programming using ladder logic.