Company Saleem Shahmeem & CO.Engineers and ConstructorsClient K-ElectricConsultant NesPakProjectInstallation, Erection & Stringing of 500KV &220KV Transmission Lines.Responsibilities are mentioned below
Preparing Timeline Schedules
Manage Resource Allocation Plans
Creat Budget Cost Estimates
Monitoring, Tracking & Controlling of Site
Progress.
Projects
120, 180, and 240 SQ-YD, 935 Bungalows.
Infrastructure Works & Development Areas (Roads, Sewerage lines, water supply lines, Commercial Markets and Parks)
Installation of 400 Electric poles (Poles height 6m, 9m & 11m)
Construction of Warehouse (70'x100')
Responsibilities
Project Scheduling.
Preparing & Verification of Bills.
Preparing Plans and BBS.
Monitoring & Controlling of Site Progress.