Engineering professional with 12 years of experience across roles like Assistant Executive Engineer, Electrical Engineer, and Site Engineer. Strong background in electrical engineering, skilled in managing sites, overseeing field operations, and leading projects to ensure quality and safety.
Electrical Infrastructure for DHA Phase VIII:
· Planning & Design: Developed and designed area-specific electrical schemes, overseeing the execution of work by contractors.
· Coordination with KE: Managed liaison with K-Electric (KE) for load sanctions and approval of electrical plans for various sectors.
· Grid Station Planning: Planned and designed future grid stations based on projected load requirements.
· Supervision & Testing: Supervised the installation, testing, and commissioning of pad-mounted transformers, switching stations, and KIOSK substations.
· KE Collaboration: Assisted the Assistant Director (E&M) in matters related to K-Electric coordination and compliance.
2. Construction of New Grid (DHA Grid 4):
KE Coordination: Secured approvals from KE for the General Layout Plan (GLO), Electrical Layout Plan (ELO), and Single Line Diagram (SLD) for the GIS-based grid station. Coordinated with contractors and consultants on technical submittals.
Factory Acceptance Testing (FAT): Conducted FAT for key components, including MV grid panels, AC/DC panels, Relay & Control Panels (RCP), Local Control Cubicles (LCC), and Bus Sectionalizers at FinTech Factory.
Cable Laying: Managed the installation of 800 mm² cables for grid station connections.
3. Technical Branch of Development Directorate:
SOP Implementation & Project Supervision: Assisted in implementing DHA SOPs, reviewed estimates and contracts, and ensured quality and compliance across projects.
Stakeholder Coordination & Project Oversight: Liaised with contractors and DHA departments, conducted site inspections, and monitored the bidding process and vendor verification.
Projects:
11 KV Distribution Lines, FIP Merged Areas, KP
132 KV Transmission Lines from Pezu to Tank , Tank to Jandola Client: FATA Secretariat Donor: USAID
Project Management: Ensured timely project delivery by defining activities, directing teams, and achieving agreed milestones.
Design Review: Collaborated with senior staff for design review, direction, and approval during development.
Project Execution: Managed all phases of 132 KV Overhead Transmission Line (OHTL) projects, including engineering, execution, and testing & commissioning.
Material Inspection: Conducted inspections of all electrical materials to ensure compliance with project specifications.
Site Supervision: Directed site teams to complete work according to approved designs and project schedules.
Strategic Planning: Developed plans and strategies for on-site execution.
Quality Assurance: Implemented QA/QC programs as per client approval, including material inspections at receipt and factory premises.
Design Documentation: Maintained records of all electrical design modifications.
Resource Management: Managed site resources and ensuring coordination between electrical and civil activities.
Drawings & Reports: Ensured preparation of marked-up drawings, as-built documents, and daily/weekly progress reports for client submission.
Transmission Line Work: Supervised tower assembly, erection, conductor stringing, OPGW and jumpering work.
Stringing & Testing: Planned and executed conductor and OPGW stringing, sagging, splicing, tower grounding and torque testing.
Technical Review: Analyzed and reviewed all technical drawings, documents, and revisions to ensure accuracy and compliance.
Construction Supervision: Oversaw construction activities, ensuring proper methods, material allocation, and adherence to approved plans.
Project Execution: Executed electrical works based on the latest approved drawings and instructions from authorized authorities.
Power Layout & Electrification: Managed the design, implementation, and installation of electrification and power layouts, including load calculation and distribution.
Site Management: Supervised and managed all electrical activities on-site, ensuring timely completion within deadlines.
Progress Reporting: Prepared and submitted daily, weekly, and monthly site progress reports.
Shop Drawings & As-Built Documentation: Implemented shop drawings on-site and incorporated field changes into as-built drawings.
Lighting Control System: Supervised the installation of lighting control systems, including pre-commissioning, commissioning, and handover.
Project Management: Managed site operations for an off-grid solar power project (hydropower and renewable energy) in Karak, KPK, in collaboration with KFW German Bank.
Site Supervision: Oversaw all site activities, prepared daily progress reports, addressed site issues, and gathered feedback from supervisors.
Reporting: Directly reported to the Electrical Manager.
Cable Work: Managed cable laying, termination, testing, and commissioning.
Transmission Line Erection: Supervised the erection of transmission line gantries, beams, and stringing works, including conductors, insulators, and string assemblies.
Equipment Installation: Oversaw the installation of Current Transformers (C.T.), Circuit Breakers (C.B.), surge arresters, and isolators.
Progress Reporting: Prepared and submitted daily, weekly, and monthly site progress reports.
Transformer Handling: Supervised the erection of power transformers, including vacuuming and dehydration processes.
Served as the Regional Coordinator for the South (Karachi Region) on the RMS (Remote Monitoring System) project in collaboration with Telenor (TP).
Managed on-site project activities, including the installation and testing of devices and systems.
Handled office-related tasks such as ATP, PAT, and FAT documentation, planning for rollout and site rectifications, and maintaining and updating all project-related data, records, and documents.
Overhauling of motors and performed maintenance and repair work on LV/MV transformers and protection relays.
Carried out testing on 132KV and 220KV switchgear, as well as batteries, chargers, and DC inverters.
Performed routine checks on gas turbines, steam turbines, HRSG BOP, and utilities.
Managed general maintenance and inspection of 100 MVA generators, including protection relays testing and alternator excitation systems, and worked oil treatment plants.
Duties & Responsibilities:
Maintenance and Operation Responsibilities of Generator , Motors , Relays , Circuit Breaker , Panels , Batteries and AVR Cards and keeping record of overall Plant Inventory.