Extrusion, Splicing & Curing process. Installation of 8 Extrusion lines as well as 199 2DL and 24 SDL Curing Presses. Successfully Achievement of productivity and quality of product. Achievement of production targets with Control inventory. Comply with all company Health, Safety and Environment as well as Work Permit, policies and procedures. Ensuring that plant and machinery are in excellent condition at all times.
Achievement of production targets as per plans
PET Bottles production at KRONES S10 and S14.
Quality control
Utilities operations
Operation, maintenance, trouble shooting, overhauling of KRONES S10 and S14 Machines.
Monitors the mechanical works and ensures compliance and conformity with the provisions of engineering techniques and procedures.
Completion of all paperwork in a timely manner.
Designing on AutoCAD and Uni-graphics 2d3d Training at KTDMC Karachi
Injection Mold Design Training at KTDMC Karachi
Comply with all company Health, Safety and Environment as well as Work Permit, policies and procedures.
Internship as Trainee Polymer Engineer at different production unit.
PVC Film Sheet Plant
PS Plant
GPPS Plant
Quality Control.
The 1st Hydrogen Peroxide H2O2 plant in Pakistan, Area-1H2 By PANAMERICAN ENTERPRISES, INC. Area-2Hydrogen Peroxide by AK-KIM Kimya Sanayi Ve Tecaret A.S., Area-3Concentration of H2O2 by SULZER, Singapore, Area-4Utilities Boiler by DDFC, Air Compressor by CompAir and R.O. Plant by WEMS and DCS by SupconJX-300 Xp Pan-American Delta-V, Foundation Field Bus System of Emerson Rosemount.. The plant has capacity of 90 M.TonsDay.I was working Errection and Commissioning Pre- Commissioning Master start up phase as a Plant Operator since 10-12-2007 up to 10-10-2008.
Plant Consists Of Following Sections
Hydrogen Production Section
Hydrogen Per-Oxide Production Section
Concentration Section
Tank Yard Filling Section
Utilities Section
The Pak-American Fertilizer plant in Pakistan having capacity of overall plant 1650 M.TonsDay, the plant has been installed with the technical Collaboration, I have Internship as a Tr.Plant Operator From 03 July 2007 to 03 Oct. 2007
Plant Consists Of Following Sections
Ammonia Production Section
Urea Production Section
Utilities Section